Hi Friends,
We are well aware that Alumina
refinery is a continuous hydro-metallurgical process involving complicated unit
operations and unit processes. Testing & commissioning is the 5th stage
in execution of new Alumina refinery which comes after Basic engineering,
Detail engineering, Procurement and Erection ensuring mechanical completion.
Safe and smooth startup of Alumina refinery with due care of human safety,
equipment, process input materials and environment are the basic objectives of
successful testing and commissioning of Alumina refinery. Thus, successful
commissioning of Alumina refinery has five basic objectives as listed below-
·
No loss time
accident,
·
No equipment
damage,
·
No risk to
environment,
·
No wastage of input
materials and
·
Stabilization of
plant within shortest period.
Sequence of testing and commissioning
of Alumina refinery include following major steps-
Field Checking and Punch
Listing:
Field checking of construction
completion status of all equipment, instruments, electrical and associated
facilities of Alumina refinery, Co-generation plant, Water supply system, Power
distribution system, Compressed air system, cooling tower and Distributed
control system is carried out before testing and commissioning of technological
plant and equipment. Based on field checking, a list of required additions /
deletions / modifications and design changes are recorded with specific
identification number for rectification on planned manner as per priority
decided by a team of senior technical professionals of the plant.
System Configuration Checking:
You must have gone through the paper on Execution of Alumina refinery on EPC Methodology. Soon after completion of erection activities and before commencement of testing and commissioning trials, system configuration checking is considered to be one of the important steps. This step is the visual inspection of
technological and services equipment as per PFDs, P&IDs, ISOs,
specifications and design drawings to ensure their readiness for cold water
trials. System configuration checking includes the verification of following-
·
Proper installation
of equipment,
·
Fixing of valves
and pipelines,
·
Alignment and
lubrication of rotating equipment,
·
Direction of
rotation of motors,
·
Sealing arrangement
of pumps,
·
Proper connections
of electrical power supply system.
Checking of Instrumentation and
Control System:
This activity is carried out to
ensure the readiness of Instrumentation and control system with respect to
following critical aspects-
·
Installation of all
instruments and controls as per P&IDs,
·
Setting of alarms
and tripping system,
·
Process and Safety interlock
system,
·
Microprocessor
signals,
·
Functioning of
local and remote sensing equipment,
·
Correct relay of
data / information from field instruments to local as well as Central control
rooms,
Checking Cleanliness of Process
Vessels and Pipelines:
This task is carried out by flushing
out the process vessels and pipelines to ensure removal of obstruction and
blockages in the process circuit just before cold water test run.
Checking of Auxiliary System:
Performance of auxiliary system like
Air conditioners, exhaust fans and connected ducts are checked to ensure
desired working environment for instruments, controls, equipment and operating
personnel.
Training of Plant Operating
Supervisors and Operators:
Objective of training of supervisory
staffs and plant operators is to guide them to commission the Alumina refinery
safely. It involves following steps-
·
Formation of team
comprising of Managers of various disciplines / departments headed by an
Expert.
·
Train the
Supervisors aiming to ‘Train the Trainer’ who will train the operators,
·
Review the startup
and commissioning procedures,
·
Educating the team
with operating and process control parameters including benefits and
consequences,
·
Provide technical
leadership to facilitate safe, reliable and steady operation of Alumina refinery.
Process and Operating Manual for
Systematic Start up:
This document includes the estimated
requirement of input materials and stepwise process sequence for meeting the
following basic requirements-
·
Planning for
required quantity of input materials,
·
Readiness of Area
wise log sheets
·
Fixing the
responsibilities of individuals in commissioning team,
·
Normal plant start
up procedure,
·
Normal shut down
procedure,
·
Emergency plant
shut down procedure,
·
Plant Inventory
procedure,
·
Procedure for
increasing the plant volume steadily,
·
Method for
increasing temperature profile of process stream,
·
Guidelines for
ensuring adequate supply of condensate to cogeneration plant,
·
Sequence for
raising concentration profile of process streams,
·
Planning for
aluminate liquor generation and seed charge to initiate generation of seed,
·
Recycling of seed
to regular precipitation circuit,
·
Production of
hydrate and product alumina.
·
Stabilization of
operation of Alumina refinery.
Start up and commissioning of Alumina Refinery:
Bauxite charge to process is considered as the zero date
for startup and commissioning of Alumina refinery which is done after caustic
concentration build up in selected process vessels to start with for generation
of spent liquor and aluminate liquor subsequently. Seed charge enhances the
precipitation efficiency thereby generation of seed and product hydrate. Steady
control on process and operating parameters stabilizes the plant resulting in
target production rate. Calciner is generally commissioned after creating
adequate stock of hydrate in the storage shed.
Performance Tests for Plant and Equipment:
Test runs are conducted with standard agreed procedure for individual plant, equipment and facilities in order to assess the guaranteed performance. However, performance tests for entire Alumina refinery are carried out after stabilization of plant operation to check the assigned production rate and efficiency parameters as agreed by technology supplier, equipment supplier and engineering consultant.
Test runs are conducted with standard agreed procedure for individual plant, equipment and facilities in order to assess the guaranteed performance. However, performance tests for entire Alumina refinery are carried out after stabilization of plant operation to check the assigned production rate and efficiency parameters as agreed by technology supplier, equipment supplier and engineering consultant.
The above stated guidelines are generally
followed for systematic testing, start up and commissioning including
establishing performance guarantee parameters of newly constructed Alumina
refinery.
Best regards.
Rajendra Kunwar
E.Mail: rajendra@ceti.co.in
Website: www.ceti.co.in
No comments:
Post a Comment