Hi Friends,
We are well aware that alumina production is a continuous
hydro-metallurgical process. The steady operation of plant and equipment
results in remarkable plant performance. At times, minor design defects causes
severe operational problems in Alumina refinery. Unsteady operation of Alumina
refinery directly impacts the efficiency of the plant. Thus, all out efforts
are made to minimize the design defects during implementation /
modification stages of plant / equipment / facilities.
In earlier posts, we have highlighted a few design defects
and the methodology to overcome those limitations as well. In present post, we
will discuss in brief a few additional design defects which have been
experienced by the author in the operative plants in India and abroad. A few
design defects are briefly outlined in subsequent paragraphs-
1.
Bauxite slurry
heating system:
Generally, heating of
ground bauxite slurry at around 100 degree centigrade is carried out either
during pre-desilication or before feeding to pre-desilication tanks. The
heating of slurry is carried out to attain the desilication temperature by
following four methods-
·
Direct injection of
steam to pre-desilication tanks,
·
Indirect heating
using Double pipe heat exchangers,
·
Indirect heating
using spiral heat exchangers and
·
Indirect heating
using Shell & tube heat exchangers.
Direct injection to bauxite slurry increases the dilution to
process and hence never considered. Double pipe heat exchanger for bauxite
slurry heating is not recommended because of acute scaling problems for the
reasons already explained in earlier post. Last two options stated above are
recommended among which the last one i.e. Shell & tube heat exchanger
is the preferred choice because of lower capital investment as well as ease in
maintenance.
2.
Schedule of pipes for
slurry handling:
Slurry generated in
red area of Alumina refinery has high abrasiveness because of presence of
silica which causes erosion of pipelines. Thus, pipelines of adequate thickness
and schedule 80 should be installed. Schedule-40 pipes should always
be avoided as it will require frequent replacement.
3.
Selection of MoC for
pumps, valves and fittings:
As such carbon steel
is the best suited material of construction (MoC) for Alumina refinery having
alkaline environment. But presence of silica causes fast erosion in stationary
as well as rotating equipment. Thus, for handling abrasive slurry in red area,
equipment / components made of carbon steel as well as Nicast are never used.
For such critical service conditions, Nihard / high nickel steel / high chrome
steel is the right choice. Never compromise on MoC of impeller and casing of
slurry pumps, connected valves and inlet Tees of slurry flash tanks
particularly for handling Bauxite slurry. Ensure the right MoC for these
critical components for steady operation of Alumina refinery.
4.
Minimum shell
thickness of Digesters:
Digesters are the
pressure vessels installed for dissolution of alumina present in bauxite in
caustic liquor. The digestion vessels are designed on the basis of its
recommended operating conditions. The shell thickness is always based on the
pressure but shell thickness is always kept more than 20 mm to take care of
any eventualities because of instrument failure and operational lapses as
well.
5.
Provision of
non-return valve in steam lines to process vessels:
Alkalinity in boiler
feed water is controlled below 0.01 gpl Na2CO3. Though direct injection of
steam to process are always avoided but a few designers keep provisions. In
such situation, non-return valve in steam line near process area is a must as
sudden drop in boiler pressure for any reason may case backing of alkaline
liquid to steam lines which may develop stress corrosion ultimately causing
sudden failure of steam line within short duration. It is essential for
safeguarding the equipment as well as safety of operating personnel in the
plant.
6.
Provision of flanges
in pipelines:
Sometimes, flanges
are not provided in slurry pipelines to minimize capital investment in project
stage. But, it cause severe operational problems because of difficulties in
cleaning of welded lines. Thus flanges must be provided at the interval of 6m
to 10m depending of practical experience operating personnel.
7.
Adequate capacity of
Evaporator Hot well:
Tail pipe of
Barometric condenser is kept submerged to a depth of about 0.50 meter in water
of Hot well of evaporation unit. The Hot well is designed to maintain adequate
seal water for circuit. The volume of Hot well is always kept more than five
times the submerged volume of leg of Barometric condenser. If water volume in
Hot well is inadequate, the vacuum seal will be broken and air drawn through
tail pipe will drastically affect the performance of evaporation unit.
8.
Minimum plate
thickness of tail pipe of Barometric condenser:
Generally, the vacuum
requirement for efficient evaporation system is 685 mm of mercury. Thus,
the minimum acceptable plate thickness for the tail pipe is 6 mm. Otherwise,
sudden increase in vacuum during start up with negligible load of non-condensable may
cause rupture of tail pipe of Barometric condenser. This problem was faced in a
newly constructed Alumina refinery which could be rectified by carrying out
modification for re-startup.
9.
RPM of impellers of
slurry pumps:
RPM of impeller is
the prime criteria for selecting the pumps for Alumina refinery. In Alumina
refinery, impeller rpm for handling bauxite residue as well as hydrate is
relatively kept at lowest possible level so as to avoid breaking of the flocs
and particles. This issue has already been discussed at length in earlier
posts.
These are just a few examples of design
defects of Alumina refinery. There are many such design defects observed in
Alumina refinery which badly affects the continuous operation of Alumina
refinery and thereby by huge monetary losses for the company. Hence, role of
Owner’s consultant becomes very important to avoid such design defects during engineering
state of execution of the plant. We would like to have your comments / remarks
for further improvement.
You may like the article on "Systematic approach for design of Slurry mixing agitator" published earlier.
You may like the article on "Systematic approach for design of Slurry mixing agitator" published earlier.
Best regards.
Rajendra Kunwar
Principal
Consultant-Engineering
CETI Gurugram, Haryana, India.
www.ceti.co.in
No comments:
Post a Comment