Operational Sequence for Startup & Commissioning of
Alumina Refinery
In this technical paper, we have elaborated the simplified
operational sequence for starting and commissioning of Alumina refinery. As
such, there may be many permutations and combinations of operational sequence
for starting and commissioning of Alumina refinery. We are presenting here one
of them which may be simple and most appropriate. The schematic diagram is
presented here under-
Start up and
commissioning of Alumina refinery is taken up after following activities-
·
Thorough checking
for Mechanical completion,
·
Readiness of raw
water supply system and DM plant,
·
Synchronization of
boilers and turbo-generators,
·
Cold water run
and
·
Hot water run.
·
Ensuring the
availability of adequate input materials.
Building up caustic concentration and simultaneously raising
its temperature to around 85 degree centigrade are pre-commissioning activities
required for startup of Alumina refinery. Sequence of caustic concentration
build up, temperature raising, start up and commissioning steps are taken up in
following sequence-
1.
Fresh caustic lye
received by road / rail tankers are stored in Caustic storage tanks (CSTs) and
6 or 7 nos. precipitators of 2nd line as 1st line precipitators shall be taken
into range for commissioning.
2.
Initially,
Evaporator feed tank, Liquor preparation tank, Digesters, Flash tanks, Heaters
and one of the Decanters are taken into range for concentration build up and
temperature raising. Accordingly closed circuit with these equipment is made by
temporary connections for circulation of liquor before start up.
3.
Water is taken in
Evaporator feed tank through temporary lines and operation of evaporator is
initiated at low vacuum and operation is stabilized slowly with boiling. This
ensures the adequate condensate supply to boilers as well as hot water for
dilution of caustic lye to around 150 to 200 gpl caustic in Liquor preparation
tank.
4.
Run the Test tank
pump at about 50% flow for filling Heaters, Digesters and Decanter connected in
the circuit. Keep the drain valves of Heaters in open condition in
the beginning for purging out entrapped air in pipelines otherwise it
may cause damage to chambers of heaters.
5.
Open steam in Live
steam heater maintaining the outlet temperature below 100 degree
centigrade.
6.
Circulation of
liquor in this circuit is continued for about 24 hours for checking the
readiness of process circuit.
7.
Start Bauxite
charging to grinding mill at about 50% digestion liquor flow and taking
charging ratio at around 0.300. Bauxite charging to grinding circuit is
considered as start of plant commissioning i.e. Zero hour of plant
commissioning.
8.
Two desilication
tanks will be filled up with slurry taking Bauxite slurry heaters into service.
After attaining about 16 hours of desilication time, temporary circuit of Red
area will be discontinued and permanent process circuit will
be energized for generation of spent liquor.
9.
Start flocculent
preparation and dosing to settler, as required.
10.
Initially Security
filters will be operating as a spool but will be taken into range afterwards
for ensuring required purity of plant liquor.
11.
Heat Interchange
Unit will be kept bypassed and filling of precipitators shall be started taking
only five (5) precipitators in range for the purpose of adequate seed
generation.
12.
Continue
circulation of Precipitation liquor through Evaporators and Digesters for
slowly raising the temperature profile of liquor.
13.
Slowly increase the
digestion liquor concentration to around 250 gpl caustic and step up charging
ratio to around 0.620 level for raising the ratio profile of aluminate liquor
to the level of pregnant liquor.
14.
Take Residue
washers into circuit.
15.
After attaining the
aluminate liquor ratio above 0.600 in feed liquor of Precipitation tanks, start
seeding with purchased solid hydrate at controlled rate for generation of seed
hydrate. For the purpose, solid hydrate will be mixed in Seed mixing tank with
Pregnant liquor and pumped to those five (5) Precipitation tanks taken in
range.
16.
Maximize charging
ratio to the desired saturation level and increase Bauxite charge at increase
digestion liquor flow.
17.
Hydrate generated
in Precipitation circuit will be used as seed till adequate hydrate is built up
in the process.
18.
Discontinue all
temporary connections and continue operation as normal by taking desired number
of equipment and vessels of one line of process circuit.
19.
Start hydrate
classification circuit and transfer of product hydrate to Hydrate storage shed.
20.
After making a
stock of adequate stock of hydrate in storage shed, commissioning of Calciner need
to be taken up for production of calcined alumina.
21.
Stabilize plant
operation for maximizing alumina production level.
We have presented the methodology for commissioning of Alumina
refinery in simplified manner for easy understanding.